Installation on behalf of Mercury Engineering Ltd

First 3 of 31 generator sets being offloaded at a multi-tenancy Data Centre in South London – Typical ASEE Ltd offload procedure Gen. set container final assembly

Fuel lines -gravity fed twin wall

Typical ‘A’ supply switchroom – and the dupllicate ‘B’ switchroon Colour Identified

Final electrical connections to multiple 3MVA generator sets – 8 x 400mm 4 core swa/LSF from output link box

Multiple HV switchboard sections

HV switchgear at final connection with 3 DNO supplies to feed several separate Client transformers.

Final connection – Rotary UPS

Installation testing UPS switchgear

‘A’ and ‘B’ Power Distribution Units feeding underfloor sockets

Option 2 – overhead busbar with 32 Amp 250 Amp