We undertook the unloading and positioning, installation, steel frame errection, acoustic cladding of multiple generators in a greenfield data centre and administration block.

We completed the installation, testing and commissioning of the MV Systems in an existing data centre.

We managed the installation, testing and commissioning of the full mechanical, sprinkler, attenuation tanks, major plant, electrical, earthing and LPS and site wide services.

We powered Schiphol's 3,000 sqm data centre! We expertly installed full electricals (HV/LV, busbar, etc.), lighting, & critical systems (fire, leak, backup).

We completed electrical installations for massive data halls (1000-3000 sqm)! We delivered comprehensive power solutions: HV & LV cabling, busbar, containment, lighting, small power, generator controls & BMS.

We ensured reliable fuel delivery for the Middenmeer Data Centre. We installed twin-wall diesel pipework with insulation for 24 backup generators.

We installed 3 generators (3.75 MVA each) in the basement, a 103,000 L double-walled fuel tank, roof-mounted cooling radiators, and 500m of cooling pipes throughout the building.

We installed all lighting and small power, primary support systems to support cable ladder rack, cable tray, cable basket, cable trunking containment, electrical panels, distribution panels and distribution boards.

We brought Primark Charleroi to light! We at ASEE Group installed all lighting, power systems, and cable management (racks, trays, etc.) for a smooth & functional retail space.