ASEE Ltd offload and positioning of first of three Containerised sets at a North of England Data Centre. Set in position and roof mounted systems being added.
Generators are designed to facilitate the use of 4000 amp resin bus bar rather than several single core armoured cables for generator output.
All three sets now in position and ASEE Ltd installation and precomissioning checks underway.
Generators are 2.5 MVA, by CTM Italy. Installation completed by ASEE Ltd in March 2007.