Midden Meer Data Centre
Project Scope
We ensure uninterrupted power supply for a critical data centre facility in Amsterdam.
Solution: We designed and installed a robust twin-wall carbon steel diesel fuel pipework system for the data centre. This system included:
Durable Pipework: High-quality, twin-wall carbon steel pipes provided strength and longevity for the fuel lines.
Effective Insulation: Meticulously installed insulation ensured optimal temperature maintenance for efficient fuel delivery.
Protective Cladding: An additional layer of cladding safeguarded the pipes from physical damage and environmental factors.
Strategic Fill Points & Controls: ASEE Group strategically positioned fill points and control systems to facilitate efficient refuelling and management of fuel flow for the 24 backup generators.
Project Overview
Installation of twin wall carbon steel diesel fuel pipework with insulation and cladding.
Position of fill points and controls serving 24 gensets.
Location
The Netherlands
Sector
Commercial