Amsterdam Data Centre

Project Scope

We installed a robust fuel delivery system for its 24 generators. This included twin-wall carbon steel diesel fuel pipes, insulated and cladded for optimal performance and protection against the elements. We also strategically positioned fill points and controls for convenient and safe refuelling. By implementing this comprehensive solution, we guarantee a reliable fuel supply to keep your data centre running smoothly – no matter what!

Project Overview

Installation of twin wall carbon steel diesel fuel pipework with insulation and cladding.

Position of fill points and controls serving 24 gensets.

Location

The Netherlands

Sector

Data Centre